Started in July 2024, the first two phases of construction of this gallery are now complete, with the creation of:
- two reinforced concrete fire-resistant separation walls of 110 m and 140 m respectively;
- vehicle and bicycle access between the tunnel and levels -2 and -3 of the Comédie car park.
The final phase includes the construction of a 130 m fire-resistant wall and will take place between July and September 2025.
The structure, currently under "Mont-Blanc" regulations, will be completely transformed into a space dedicated to soft mobility, contributing to the creation of new regulations that did not previously exist.
Congratulations to our teams involved in this large-scale project!
Creating safe and innovative cycle paths to improve urban mobility makes a difference!