This second symbolic phase was an engineering challenge, combining precision—with the millimetric sliding of the deck onto the second part of the bridge—within a constrained urban environment.
Next step: jacking down
Congratulations to all the teams involved for the successful completion of this key milestone in the project!
Project owner: Brest Métropole - Brestfr
Delegated project owner: BMa - Brest Métropole Aménagement
Project management: MobiBrest, SYSTRA (lead), SCE Aménagement & Environnement, B3i, FERRAND-SIGAL Architectes & Associés, Super8, LA/BA architectes
Contractor consortium: ETPO, a subsidiary of Groupe ETPO - Eiffage Métal
Earthworks: Spie batignolles Valérian
Credit: Cédric Joie SAP Photographie