Completed installations:
- The tailrace and drainage canal
- The water intakes
- The spillway, consisting of 3 gates, each 11 meters wide, with a total capacity of 2,745 m³ per second
- The transformer substation and 90,000 V power line
Ongoing installations: The assembly of the 22 MW horizontal-axis Kaplan turbines is currently underway.
This dam is designed to deliver 44 MW of power to the Ivorian interconnected grid, thereby strengthening Côte d'Ivoire's decarbonized electricity production capacity.
A design-build project with RMT for Ivoire Hydro Energy.