Eiffage Metal will take part in refurbishing the Austerlitz railway station

They are scheduled over 32 months, and should be completed by July 2020. They involve the upgrading of the large and small station concourses covering 15,000 m² in all, and include renovation work on the historic steel frame and glass and zinc roof, built in 1869 and measuring 280 m by 53 m.
Eiffage Metal's package includes removal of asbestos-containing glazing panels, lead removal, painting and reinforcement of the steel structures, refurbishment or the glazing and zinc roof.